Churchwell house #58
Finished installing all closet shelving
Trimmed w/h shelf
Started installing kitchen cabinets
Installed bathroom hardware
Installed vanity
Insulated attic stairs
Installed a/c vent covers
Continued caulking trim & shelving
Started installing door stops
Started building storage shed
Tort house #59
Installed soffits with vents
Finished installing microwave, bathroom & closet supports
Insulated behind bath tub
Installed construction locks
Started installing porch ceiling
Installed drip edge
Put hvac unit in attic
Installed attic stairs
Installed hvac vents
Installed both bath room fans
Pizza for lunch today with fruit & assorted desserts.Thanks to the Bible Explorers class of Acton Methodist.