Wednesday, October 15, 2025

#122 - 3713 Canyon Rd

We had 21 construction volunteers, 4 office volunteers and 1 lunch volunteer today.

    Today we put up as much of the siding as we could with the scaffolding still in place. We installed the trim around the porch, found more blocking to install and put the tub in the bathroom. The fence crew set the post for the side fence line. In the warehouse we installed the vents in the soffit pieces and have them ready to install and continued working on the plenums for the A/C.

Lunch was provided by the Granbury Seventh-day Adventist Church.
Thank you for a delicious lunch.

See you Saturday at 8:30!

photos by Molly